Get Ready for the Building Inspector

Posted By John Rinaldi - Architect On October 16, 2007 @ 7:53 pm In City & County Agencies, Construction | 1 Comment

Before concrete is poured for any Project, a Building Inspector will visit the site to check the job. You should prepare for the following:
1. Have a signed Soils Report ready for him to read;
2. Any saturation of the soil in that Report will be checked;
3. He will check a stamped, approved set of drawings, which should always be ready
and accessible to all inspectors;
4. He will check the foundation plan against what is laid out in the foundation
a. Depth of footings and plate
b. Anchor bolt spacing
c. Holdown hardware
d. Shearwall lengths and placement
e. Slab steel and spacing
f. Steel slab concrete chocks to raise re-bar, for concrete to fully engulf
re-bar;
5. If any of the above is not to his satisfaction, he will leave a correction sheet
with items he feel must be corrected;
6. Usually, a telephone number is on the correction sheet, to call for re-
inspection.

For more architectural advice and articles, to see one of our many projects, or to learn more about our office and the services we offer, go to our main website: Architect Atascadero


Article printed from : http://www.rinaldiaia.com/blog

URL to article: http://www.rinaldiaia.com/blog/2007/10/get-ready-for-building-inspector.htm

Copyright © 2010 Architect For Atascadero, Paso Robles, San Luis Obispo. All rights reserved.